Set purchase reviewers and budget checks
Make the review route and budget basis clear before a purchase progresses.
In this lesson
Set purchase reviewers and budget checks
Make the review route and budget basis clear before a purchase progresses.
Before you start
Identify who requests the purchase, reviews it, owns procurement, confirms the budget, receives delivery and checks the bill. A job responsibility and an app permission are different: reviewers also need the appropriate workroom access.
Check the existing review route
1. Open Procure → Approvals. Use My Queue for assigned decisions and Submitted or All Approvals to find the exact request’s history. Read its stage, items, amount and Previous decisions; an empty queue does not mean every request is approved.
2. Return to the source request and check its current approval and fulfilment states. For an approved request waiting in Procurement intake, use Assign owner, choose the agreed responsible person and select Assign. Reopen the request to check the owner. Ownership does not itself authorise an order or payment.
Configure a custom route only when needed
3. Open Approvals → Workflows. Check the existing route first; an empty custom-workflow list can still use default routing. If the existing route meets your process, skip steps 4–6 and continue to the budget check in step 7. Create a custom workflow only when your agreed process needs different stages or scope.
4. Select New workflow. Enter Workflow name, Purpose, Record type, Minimum amount, Maximum amount, Currency and Request source. Leaving amount fields empty applies the route to every value, so review the scope carefully.
5. Complete Approval stages in order. For each stage, enter Stage name, Who approves, Decision rule and Due after in hours. Use Add stage for another stage. Specific workroom members exposes Add an approver; Minimum number must approve requires an achievable Approvals required count.
About this example: The form separates amount, currency and request-source scope from ordered approval stages. Who approves, Decision rule and Due after are visible here. This incomplete form has Create workflow disabled; it does not show a saved route or a successful routing test.

Verify the route before checking the budget
6. Review the full route and select Create workflow. Find it again and check its scope, stages and eligible reviewers. Use an appropriate test request to confirm actual routing before relying on the workflow.
Check the budget for the same purchase
7. Open Procure → Budgets → Availability. Match department, account or category mapping, currency, period and amount with the governing Finance budget version. Check its state before relying on Available; a draft allocation is not an active allowance.
About this example: The upper demo card shows a USD100 budget but Draft and Not active; the lower card displays Available USD100. Both use the label BUD-001, so the label alone does not identify the governing Finance version. Requested, Reserved, Committed and Actual are separate measures; this example does not demonstrate nonzero commitments.

Reconcile commitments and remaining responsibilities
8. Compare Requested, Reserved, Committed and Actual with the underlying request, order and financial records. Use Commitments and Exceptions to inspect related entries. Do not count a request and its resulting order twice, or add an entire order to costs that already include part of it.
Work one review and budget decision
In a fictional Brookfield design, a USD 20–30 purchase request goes first to Budget review, then Procurement preparation review. Each stage has one different verified eligible member, Any one approver, and Due after 24 hours. The first approval does not complete the second stage; the due-hours field does not prove automatic approval or escalation. Do not create the route until its scope is approved and isolated from unrelated requests. If you choose Minimum number must approve, the required count must not exceed eligible selected reviewers.
For the same example, suppose the governing budget is USD 30 and an authorised USD 23 order creates one outstanding commitment, with no actual cost yet. Under the example policy—budget minus actuals minus outstanding commitments—headroom is USD 7. If a later matched USD 23 bill becomes actual and that same commitment is fully relieved, headroom remains USD 7: 30 − 23 − 0. Do not subtract the old full commitment again and report −16.
These are conditional example figures, not a saved order or a universal Workroomly calculation. Check the actual policy, governing version, source records and documented relief. Approval, budget headroom, procurement ownership and cash availability remain separate decisions.
Expected result
The purchase has a clear reviewer route, a procurement owner and an identified budget basis for the next decision.
For temporary cover: use Approvals → Delegations → New delegation. Review Delegate to, Approval scope, Starts and Ends before Create delegation, then reopen it. Delegation covers assigned approvals during the chosen period; it is not a permanent workflow change or permission to share a sign-in.
Continue learning
In this series: Manage purchasing — guide 3 of 17.
Turn what you learned into the way the team works.
Mark this lesson complete once the workflow exists in your workspace—not simply when you reach the bottom.