Turn spend analysis into a sourcing plan

Workroomly Editorial
Begin the lesson ↓

Share this resource

Copy the link to share this page with your team.

Use comparable purchase data to choose a category action and keep planned savings separate from realised results.

In this lesson

Turn spend analysis into a sourcing plan

Use comparable purchase data to choose a category action and keep planned savings separate from realised results.

Before you start

Define the business question and reporting basis: entity, category, dates, source state, currency and tax treatment. Ordered value, accepted value, approved invoices and cash paid are different measures; do not add them as separate purchases.

Read the reports on their own terms

1. Open Procure → Spend under Insights. Review Overview, Suppliers, Categories and Contracts, reading each helper definition and active search before comparing amounts.

2. Check the date scope and ranking limit on each view. In particular, Request estimates by category is not the same measure as Finance-approved invoice value. Matching totals in one small period do not establish that two reports use the same population.

3. Reconcile the relevant source records by supplier identifier, invoice, line and version. Keep credits and their references. Investigate apparent duplicates without deleting legitimate repeated purchases, and keep source currency separate from any approved reporting-currency conversion.

4. Decide the improvement you want: reliable supply, compatible demand consolidation, fewer deliveries, better agreement use or an eligible backup. Compare equivalent quality and service, not unit price alone.

Save the category strategy

5. Open Procure → Categories → Strategies. Search for the intended strategy. If it already exists, inspect its saved scope and current plan, then skip steps 6–7 and continue at step 8. Otherwise, select New Strategy.

6. Complete Category, Strategy title, Owner, Commercial objectives, Market context, Preferred suppliers, Contract coverage (%) and Review date. Give coverage a defined population and period; do not assume the field calculates it automatically. Retain action owners, source references and implementation dates in your supporting plan.

7. Select Save strategy, find its exact title and reopen it to check the retained details. A preferred-supplier selection does not itself qualify that supplier or award an order.

Record a justified savings pipeline

8. Open Spend → Savings and check the award-and-method pair for an existing claim. If the claim exists, inspect its current details and state rather than repeating step 9 to create the same benefit again. For a new supported claim, select Record savings.

9. Confirm Approved award, choose the appropriate Savings method, and enter the documented Approved baseline in the award’s currency. Review the source-derived award amount, then select Create savings pipeline. Reopen the claim and check its baseline, awarded amount, pipeline and actual realised value.

Expected result

The category plan has a clear basis, owner and review point, while any savings claim is traceable to its award and baseline.

Remember: A lower spend total may reflect lower volume rather than a price saving. Realised savings need eligible actual activity and validation under your agreed method, including implementation costs. Do not change the baseline or method to bypass a duplicate warning or make an unsupported benefit look achieved.

Separate forecast from the validated result

Worked comparison on one consistent scope

The original Harborview fictional paper case uses 200 equivalent binders and four deliveries. Its approved HB-BASE-01 baseline is 200 × USD 5 + 4 × USD 20 = USD 1,080. HB-AWARD-01 is 200 × USD 4.40 + 4 × USD 15 = USD 940. A separate approved implementation cost is USD 20. These are not selectable application records.

Measure Calculation Meaning
Gross forecast 1,080 − 940 = USD 140 Full planned award comparison, not realised benefit.
Net forecast 140 − 20 = USD 120 Includes the separately stated implementation cost.
First review baseline 50 × 5 + 20 = USD 270 Only the first 50 accepted units and one delivery.
First review eligible cost Approved purchase bill 235 + implementation bill 20 = USD 255 The case's approved-bill method includes both; both remain unpaid.
Net validated benefit 270 − 255 = USD 15 Supplied paper validation, not automatic Workroomly realisation or cash saved.
Remaining forecast USD 105 15 realised + 105 forecast = 120, not 135. Future uptake is still conditional.

Keep source measure and dates with the strategy. For example: objective 200 equivalent binders; baselineHB-BASE-01; awardHB-AWARD-01; review result 50 accepted, USD 15 net validated, zero paid; next checkactual remaining deliveries, acceptance and costs. Do not enter the net 120 into a field defined as baseline minus award without verifying how that method treats implementation costs.

Your real saved strategy should have the agreed owner and review date. Your savings record needs its own supported award/method and evidence; neither a lower spend total nor a preferred-supplier selection proves a saving.

Continue learning

Continue learning

In this series: Manage purchasing — guide 16 of 17.

Turn what you learned into the way the team works.

Mark this lesson complete once the workflow exists in your workspace—not simply when you reach the bottom.